Report No.

400

Discipline/Origin

Drilling
No origin

Well

Shrek
6507/5-9 S, 6507/5-9 A

Date created

2020/03/13
2095 days ago

Project Phase

Planning
Project Phase

LL Type/Classification

Planning
Negative

Deepsea Nordkapp


Section N/A. What happened:
Cost approval process time consuming; missing quotes/contracts, many outdated documents on Sharepoint (PP?)

What Was Learned

MSR to be checked against quotes and or frame agreement by cost controller and lead engineer. MSR should be requested two months before spud
Kick off meeting with service coordinator and cost controller from service
Review of AfE and follow RACI process
All contracts, pricelists, quotes and deals uploaded to Projectplace
Pricelists needs to be updated annually by service companies, instead of having to find current escalation rate in other documents (different escalation rates for personnel and equipment makes process time consuming)
Make folders more intuitive in Contract Folder on Sharepoint.

What Actions Are Required

MSR to be checked against quotes and or frame agreement by cost controller and lead engineer. MSR should be requested two months before spud
Kick off meeting with service coordinator and cost controller from service
Review of AfE and follow RACI process
All contracts, pricelists, quotes and deals uploaded to Projectplace
Pricelists needs to be updated annually by service companies, instead of having to find current escalation rate in other documents (different escalation rates for personnel and equipment makes process time consuming)
Make folders more intuitive in Contract Folder on Sharepoint.